Construction updates
- MiriaIoannou
- Jul 3
- 3 min read
170 Roehampton - Week of July 6

Major Work:
The main activity is formwork for above grade building structure.
Building envelope in progress with the installation of window wall at Podium levels on L4-L5
Regular working hours onsite will be starting at 6am to 5pm daily but expect Saturday work from 7am-5pm (as per City of Toronto Noise Exemption Permit).
Traffic Events:
All gates are active – Gate #1 and #2 via Roehampton Ave and Gate #3 and Gate #4 via Redpath Ave
Concrete deliveries – we will have concrete trucks daily and the number of trucks will vary depending on the daily needs.
Concrete trucks coming to the site Monday-Friday for regular pours (walls/columns). We anticipate 1-5 trucks per day, which will be entering and exiting the site through Gate #2 via Roehampton Avenue.
Slab pours on Monday (weather permitted), and we anticipate 15 concrete trucks per day, which will be entering and exiting the site through Gate #2 via Roehampton Avenue.
Flatbed trailer truck delivering electrical equipment Monday at 9am, through Gate #2 via Roehampton Avenue
53’ flatbed trailer truck delivering rebar Tuesday/Thursday at 7am (weather permitting),through Gate #2 via Roehampton Avenue
53’ trailer truck delivering windows Wednesday/Thursday at 9am and Thursday-Friday from 3pm-7pm, through Gate #2 via Roehampton Avenue
Flatbed truck delivering plumbing material Monday/Wednesday/Friday at 7am, through Gate #2 via Roehampton Avenue and Gate #3 via Redpath Avenue
Flatbed truck delivering CMU blocks and mortar Monday/Friday at 7am, through Gate #3 via Redpath Avenue
Flatbed trucks delivering and demobilizing formwork materials. We expect 1-2 loads daily, which will be entering and exiting the site through Gate #2 via Roehampton Avenue.
Expect periodic small deliveries into the site from Gate #1 and #2 via Roehampton Avenue and Gate #3 and Gate #4 via Redpath Ave

241 Redpath - weekly construction update & lookahead
July 6-10, 2026
Current Site Activities
Work on site is progressing as we continue formwork for building’s foundation.
• Concrete
Concrete pours ongoing
Rebar deliveries ongoing
• Site Access and Trucking
Traffic control personnel remain in place at 241 Redpath Ave to support truck
movements related to material deliveries.
Week Ahead: July 6th th to July 10th
Next week’s work will focus on formwork for building’s foundation.
▪ Concrete pours – expected daily
▪ Concrete truck/ should be expected between 7:00 AM and 5:00 PM.
o Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing
guard when increased traffic is to be expected
• Rebar Deliveries
▪ Increased rebar truck traffic should be expected between 7:00AM-5:00PM
Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing guard when
increased traffic is to be expected
• General Trucking
o Beyond the excavation trucking noted above, all other truck traffic this week is
expected to be infrequent.
o Traffic control will continue to ensure safe access for pedestrians, cyclists, and
vehicles around the site.
o Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing
guard when increased traffic is to be expected
o All trades reminded daily about no truck staging allowed on Erskine
Community Considerations
We remain committed to minimizing construction impacts on the neighborhood.
• Noise: Excavation/Shoring and material deliveries may generate typical construction noise;
however, all activities will take place within permitted working hours.
• Safety: Dedicated traffic control personnel will be present during key operations to ensure
safe passage for all road users.





Comments