APRIL 13 week


170 ROEHAMPTON

  • Major Work:

    • The main activity is formwork for above grade building structure.

    • Regular working hours onsite will be starting at 7am to 5pm daily but expect Saturday work from 9am-5pm.

  • Traffic Events:

    • Update: Gate #1 and #2 via Roehampton Ave and Gate #3 via Redpath Ave will be the ONLY active gates to the site – ALL deliveries and site traffic will be coming in/out the site through Gate #1, #2 and #3.

    • Gate #4 via Redpath Ave remains temporarily closed – no site traffic from Redpath Ave next week.

    • Redpath Ave Overhead Protection and Temporary Hoarding: work is completed – bi-fold and sliding gates for Gate #3 and #4 on Redpath Ave will be installed in the next two weeks.

    • Concrete deliveries – we will have concrete trucks daily and the number of trucks will vary depending on the daily needs.

    • Concrete trucks coming to the site Monday-Friday for regular pours (walls/columns). We anticipate 1-5 trucks per day, which will be entering and exiting the site through Gate #2 via Roehampton Avenue.

    • Slab pours on Wednesday/Thursday (weather permitted), and we anticipate 5-15 concrete trucks per day, which will be entering and exiting the site through Gate #2 via Roehampton Avenue.

    • Mobile Concrete Pumps with be setup on Wednesday/Thursday morning (weather permitted) to facilitate the concrete pour.

    • 53’ trailer truck delivering rebar Monday/Wednesday-Friday at 7am (weather permitted),through Gate #2 via Roehampton Avenue

    • Flatbed trucks delivering formwork materials. We expect 1-2 loads daily, which will be entering and exiting the site through Gate #1 and #2 via Roehampton Avenue.

    • Expect periodic small deliveries into the site from Gate #1 and #2 via Roehampton Avenue.

  • Advance notices:

    • n/a

 Kris Stoja | Site Superintendent

CLARK CONSTRUCTION MANAGEMENT INC.

Cell: (437) 553-0139 | email: kStoja@clarkcm.ca


241 REDPATH


Current Site Activities

Work on site is progressing as we continue formwork for building’s foundation.

• Concrete

o Concrete pours ongoing

o Rebar deliveries ongoing

• Site Access and Trucking

o Traffic control personnel remain in place at 241 Redpath Ave to support truck

movements related to excavation, and material deliveries.

Week Ahead: April 13th to April 17th, 2026,

Next week’s work will focus on formwork for building’s foundation.

• Concrete Works

o April 13th to April 17th

▪ Concrete pours – April 11th & 17th 2026

▪ Increased concrete truck traffic should be expected between 7:00 AM and

5:00 PM.o Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing

guard when increased traffic is to be expected

• Rebar Deliveries

o April 13th to April 17th 2026

▪ Increased rebar truck traffic should be expected between 7:00 AM and 5:00PM

Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing guard when

increased traffic is to be expected

• General Trucking

o Beyond the excavation trucking noted above, all other truck traffic this week is

expected to be infrequent.

o Traffic control will continue to ensure safe access for pedestrians, cyclists, and

vehicles around the site.

o Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing

guard when increased traffic is to be expected

o All trades reminded daily about no truck staging allowed on Erskine

Community Considerations

We remain committed to minimizing construction impacts on the neighborhood.

• Noise: Excavation/Shoring and material deliveries may generate typical construction noise;

however, all activities will take place within permitted working hours.

• Safety: Dedicated traffic control personnel will be present during key operations to ensure

safe passage for all road users.


Kieran Charnock, Site Superintendent