Construction updates
- MiriaIoannou
- 1 day ago
- 3 min read

APRIL 13 week
170 ROEHAMPTON
Major Work:
The main activity is formwork for above grade building structure.
Regular working hours onsite will be starting at 7am to 5pm daily but expect Saturday work from 9am-5pm.
Traffic Events:
Update: Gate #1 and #2 via Roehampton Ave and Gate #3 via Redpath Ave will be the ONLY active gates to the site – ALL deliveries and site traffic will be coming in/out the site through Gate #1, #2 and #3.
Gate #4 via Redpath Ave remains temporarily closed – no site traffic from Redpath Ave next week.
Redpath Ave Overhead Protection and Temporary Hoarding: work is completed – bi-fold and sliding gates for Gate #3 and #4 on Redpath Ave will be installed in the next two weeks.
Concrete deliveries – we will have concrete trucks daily and the number of trucks will vary depending on the daily needs.
Concrete trucks coming to the site Monday-Friday for regular pours (walls/columns). We anticipate 1-5 trucks per day, which will be entering and exiting the site through Gate #2 via Roehampton Avenue.
Slab pours on Wednesday/Thursday (weather permitted), and we anticipate 5-15 concrete trucks per day, which will be entering and exiting the site through Gate #2 via Roehampton Avenue.
Mobile Concrete Pumps with be setup on Wednesday/Thursday morning (weather permitted) to facilitate the concrete pour.
53’ trailer truck delivering rebar Monday/Wednesday-Friday at 7am (weather permitted),through Gate #2 via Roehampton Avenue
Flatbed trucks delivering formwork materials. We expect 1-2 loads daily, which will be entering and exiting the site through Gate #1 and #2 via Roehampton Avenue.
Expect periodic small deliveries into the site from Gate #1 and #2 via Roehampton Avenue.
Advance notices:
n/a
Kris Stoja | Site Superintendent
CLARK CONSTRUCTION MANAGEMENT INC.
Cell: (437) 553-0139 | email: kStoja@clarkcm.ca
241 REDPATH

Current Site Activities
Work on site is progressing as we continue formwork for building’s foundation.
• Concrete
o Concrete pours ongoing
o Rebar deliveries ongoing
• Site Access and Trucking
o Traffic control personnel remain in place at 241 Redpath Ave to support truck
movements related to excavation, and material deliveries.
Week Ahead: April 13th to April 17th, 2026,
Next week’s work will focus on formwork for building’s foundation.
• Concrete Works
o April 13th to April 17th
▪ Concrete pours – April 11th & 17th 2026
▪ Increased concrete truck traffic should be expected between 7:00 AM and
5:00 PM.o Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing
guard when increased traffic is to be expected
• Rebar Deliveries
o April 13th to April 17th 2026
▪ Increased rebar truck traffic should be expected between 7:00 AM and 5:00PM
Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing guard when
increased traffic is to be expected
• General Trucking
o Beyond the excavation trucking noted above, all other truck traffic this week is
expected to be infrequent.
o Traffic control will continue to ensure safe access for pedestrians, cyclists, and
vehicles around the site.
o Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing
guard when increased traffic is to be expected
o All trades reminded daily about no truck staging allowed on Erskine
Community Considerations
We remain committed to minimizing construction impacts on the neighborhood.
• Noise: Excavation/Shoring and material deliveries may generate typical construction noise;
however, all activities will take place within permitted working hours.
• Safety: Dedicated traffic control personnel will be present during key operations to ensure
safe passage for all road users.
Kieran Charnock, Site Superintendent
BLUESCAPE CONSTRUCTION