170 Roehampton - Week of July 6


  • Major Work:

    • The main activity is formwork for above grade building structure.

    • Building envelope in progress with the installation of window wall at Podium levels on L4-L5

    • Regular working hours onsite will be starting at 6am to 5pm daily but expect Saturday work from 7am-5pm (as per City of Toronto Noise Exemption Permit).

  • Traffic Events:

    • All gates are active – Gate #1 and #2 via Roehampton Ave and Gate #3 and Gate #4 via Redpath Ave

    • Concrete deliveries – we will have concrete trucks daily and the number of trucks will vary depending on the daily needs.

    • Concrete trucks coming to the site Monday-Friday for regular pours (walls/columns). We anticipate 1-5 trucks per day, which will be entering and exiting the site through Gate #2 via Roehampton Avenue.

    • Slab pours on Monday (weather permitted), and we anticipate 15 concrete trucks per day, which will be entering and exiting the site through Gate #2 via Roehampton Avenue.

    • Flatbed trailer truck delivering electrical equipment Monday at 9amthrough Gate #2 via Roehampton Avenue

    • 53’ flatbed trailer truck delivering rebar Tuesday/Thursday at 7am (weather permitting),through Gate #2 via Roehampton Avenue

    • 53’ trailer truck delivering windows Wednesday/Thursday at 9am and Thursday-Friday from 3pm-7pmthrough Gate #2 via Roehampton Avenue

    • Flatbed truck delivering plumbing material Monday/Wednesday/Friday at 7amthrough Gate #2 via Roehampton Avenue and Gate #3 via Redpath Avenue

    • Flatbed truck delivering CMU blocks and mortar Monday/Friday at 7amthrough Gate #3 via Redpath Avenue

    • Flatbed trucks delivering and demobilizing formwork materials. We expect 1-2 loads daily, which will be entering and exiting the site through Gate #2 via Roehampton Avenue.

    • Expect periodic small deliveries into the site from Gate #1 and #2 via Roehampton Avenue and Gate #3 and Gate #4 via Redpath Ave

 

 




241 Redpath - weekly construction update & lookahead

July 6-10, 2026

Current Site Activities

Work on site is progressing as we continue formwork for building’s foundation.

• Concrete

  Concrete pours ongoing

Rebar deliveries ongoing

• Site Access and Trucking

Traffic control personnel remain in place at 241 Redpath Ave to support truck

movements related to material deliveries.

Week Ahead: July 6th th to July 10th

Next week’s work will focus on formwork for building’s foundation.

▪ Concrete pours – expected daily

▪ Concrete truck/ should be expected between 7:00 AM and 5:00 PM.

o Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing

guard when increased traffic is to be expected

• Rebar Deliveries

▪ Increased rebar truck traffic should be expected between 7:00AM-5:00PM

Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing guard when

increased traffic is to be expected

• General Trucking

o Beyond the excavation trucking noted above, all other truck traffic this week is

expected to be infrequent.

o Traffic control will continue to ensure safe access for pedestrians, cyclists, and

vehicles around the site.

o Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing

guard when increased traffic is to be expected

o All trades reminded daily about no truck staging allowed on Erskine

Community Considerations

We remain committed to minimizing construction impacts on the neighborhood.

• Noise: Excavation/Shoring and material deliveries may generate typical construction noise;

however, all activities will take place within permitted working hours.

• Safety: Dedicated traffic control personnel will be present during key operations to ensure

safe passage for all road users.



 





 
 
 