top of page
Search

Construction updates

MiriaIoannou
6 days ago
3 min read

170 Roehampton - Workplan week of Oct 13-16



Work Plan and Traffic Updates for the week of October 12th:

  • Major Work:

    • The main activity is formwork for tower structure.

    • Building envelope in progress with the installation of window wall at Podium levels on L13-L14

    • Regular working hours onsite will be starting at 6am to 5pm daily but expect Saturday work from 7am-5pm (as per City of Toronto Noise Exemption Permit).

    • Site will be closed on Monday October 12th for Thanksgiving Day Holiday.

  • Traffic Events:

    • All gates are active – Gate #1 and #2 via Roehampton Ave and Gate #3 and Gate #4 via Redpath Ave

    • Concrete deliveries – we will have concrete trucks daily and the number of trucks will vary depending on the daily needs.

    • Slab pours on Friday (weather permitted), and we anticipate 15 concrete trucks, which will be entering and exiting the site through Gate #2 via Roehampton Avenue.

    • Concrete trucks coming to the site Tuesday-Wednesday (weather permitted) for regular pours (walls/columns). We anticipate 5-9 trucks per day, which will be entering and exiting the site through Gate #2 via Roehampton Avenue.

    • Tri-axle truck remove and return 40-yard mix-waste bin Monday-Friday through Gate #1 via Roehampton Avenue and Gate #4 via Redpath Avenue

    • 53’ flatbed trailer truck delivering rebar Tuesday/Thursday at 6am (weather permitted),through Gate #2 via Roehampton Avenue

    • Cube truck delivering window wall panels Friday between at 8am-1pm, and we anticipate6-7 trucks per day through Gate #3 via Redpath Avenue

    • Flatbed truck delivering plumbing material Tuesday/Friday at 7am, through Gate #2 via Roehampton Avenue and Gate #3 via Redpath Avenue

    • Flatbed truck delivering stud framing and drywall material Tuesday/Thursday at 8am,through Gate #2 via Roehampton Avenue and Gate #3 via Redpath Avenue

    • Flatbed trucks delivering and demobilizing formwork materials. We expect 1-2 loads daily, which will be entering and exiting the site through Gate #2 via Roehampton Avenue.

    • Expect periodic small deliveries into the site from Gate #1 and #2 via Roehampton Avenue and Gate #3 and Gate #4 via Redpath Ave 


Thank you for your ongoing patience and cooperation.

 

Regards,

 




241 Redpath - October 9-16

Weekly Construction Update & Lookahead

October 9th, 2026

Current Site Activities

• Concrete & Formwork

o Ground Floor to L1 Mezz ongoing

o Concrete pours ongoing daily

o Rebar deliveries ongoing daily

• Site Access and Trucking

o Traffic control personnel remain in place at 241 Redpath Ave to support truck

movements related to material deliveries.

Week Ahead: October 13th to October 16th, 2026

Next week’s work will focus on formwork for building’s foundation.

• Concrete Works

o October 13th to October 16th, 2026

▪ Concrete pours – Daily

▪ Concrete truck/ should be expected between 7:00 AM and 7:00 PM.o Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing

guard when increased traffic is to be expected

• Rebar Deliveries

o October 13th to October 16th, 2026

▪ Increased rebar truck traffic should be expected between 7:00AM - 5:00PM

Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing guard when

increased traffic is to be expected

• General Trucking

o Beyond the excavation trucking noted above, all other truck traffic this week is

expected to be infrequent.

o Traffic control will continue to ensure safe access for pedestrians, cyclists, and

vehicles around the site.

o Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing

guard when increased traffic is to be expected

o All trades reminded daily about no truck staging allowed on Erskine

Community Considerations

We remain committed to minimizing construction impacts on the neighborhood.

• Noise: Formwork and material deliveries will generate typical construction noise; however,

all activities will take place within permitted working hours.

• Safety: Dedicated traffic control personnel will be present during key operations to ensure

safe passage for all road users.


Kieran Charnock

Site Superintendent




 
 
 

Comments


bottom of page