MARCH 16 WEEK


170 ROEHAMPTON

Work Plan and Traffic Updates for the week of March 16th:

  • Major Work:

    • The main activity is formwork for above grade building structure.

    • Regular working hours onsite will be starting at 7am to 5pm daily but expect Saturday work from 9am-5pm.

  • Traffic Events:

    • No changes: Gate #1 and #2 via Roehampton Ave will be the ONLY gates to the site – ALL deliveries and site traffic will be coming in/out the site through Gate #1 and #2.

    • Gate #3 via Redpath Ave remains temporarily closed – no site traffic from Redpath Ave next week.

    • Redpath Ave Overhead Protection and Temporary Hoarding: work is in progress and activity anticipated to complete next week. Measures will be taken for traffic control but expect periodic traffic delays on Redpath Avenue.

    • Roehampton and Redpath road work: City of Toronto contractor scheduled to mobilize end of the week and start work on the road to bring permanent site services to the project – lane reductions/closures to be expected and traffic delays on Roehampton Ave and Redpath Ave.

    • Concrete deliveries – we will have concrete trucks daily and the number of trucks will vary depending on the daily needs.

    • Concrete trucks coming to the site Monday-Friday for regular pours (walls/columns). We anticipate 1-5 trucks per day, which will be entering and exiting the site through Gate #2 via Roehampton Avenue.

    • Slab pours on Tuesday-Wednesday/Friday (weather permitted), and we anticipate 5-15 concrete trucks per day, which will be entering and exiting the site through Gate #2 via Roehampton Avenue.

    • Mobile Concrete Pumps with be setup on Tuesday-Wednesday/Friday morning (weather permitted) to facilitate the concrete pour.

    • 53’ trailer truck delivering rebar Monday-Wednesday at 7am (weather permitted), through Gate #2 via Roehampton Avenue

    • Flatbed trucks delivering formwork materials. We expect 1-2 loads daily, which will be entering and exiting the site through Gate #1 and #2 via Roehampton Avenue.

    • Expect periodic small deliveries into the site from Gate #1/#2 via Roehampton Avenue.

Kris Stoja | Site Superintendent

CLARK CONSTRUCTION MANAGEMENT INC.

Cell: (437) 553-0139 | email: kStoja@clarkcm.ca



241 REDPATH

Next week’s work will focus on formwork for building’s foundation.

• Concrete Works

o Mar 16th to Mar 20th

▪ Concrete pours Mar 16th

, Mar 17th , Mar 20th

▪ Increased concrete truck traffic should be expected between 7:00 AM and

5:00 PM.

▪ Crane errection scheduled for weekend of Mar 28/29o Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing

guard when increased traffic is to be expected

• Rebar Deliveries

o Mar 16th to Mar 20th

▪ Increased rebar truck traffic should be expected between 7:00 AM and 5:00 PM.

Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing guard when

increased traffic is to be expected

• General Trucking

o Beyond the excavation trucking noted above, all other truck traffic this week is

expected to be infrequent.

o Traffic control will continue to ensure safe access for pedestrians, cyclists, and

vehicles around the site.

o Traffic control personnel to remain at Erskine & Redpath crosswalk with crossing

guard when increased traffic is to be expected

o All trades reminded daily about no truck staging allowed on Erskine

Community Considerations

We remain committed to minimizing construction impacts on the neighborhood.

• Noise: Excavation/Shoring and material deliveries may generate typical construction noise;

however, all activities will take place within permitted working hours.

• Safety: Dedicated traffic control personnel will be present during key operations to ensure

safe passage for all road users.


Kieran Charnock, Site Superintendent